Campbelltown City Council — Development Application Data

Development assessment times run longer in Campbelltown City Council than in many comparable Sydney councils, with the median DA taking 58 days to determine. The council has processed 4514 applications since 2021, with 1987 lodged in the past year alone. Activity spans a broad range, from smaller residential work through to major projects: 1351 applications valued under $100k, 1479 between $100k and $500k, and 228 exceeding $5M. Development standard variations under Clause 4.6 appear in just 2.55% of applications. The most common development types are dual occupancies (525 applications), alterations and additions (355), subdivisions (320), and change of use proposals (104), though 2974 applications fall into other categories. Understanding how your specific project aligns with Campbelltown's assessment priorities and timelines matters before lodgement. A Plan Advice AI-powered assessment for your Campbelltown City Council property delivers that insight in seconds.

DAs on file
4,658
Since 2021
Lodged last 12m
1,983
Median assessment
58 days
FY FY25-26
Clause 4.6 rate
2.6%
Development standard variations

How long a DA takes in Campbelltown City Council, and who decides it

Counted from every application Campbelltown City Council determined in the last 5 years, as published in the NSW Planning Portal open data. Timelines are lodgement to determination, so they include the time spent waiting on the applicant.

Median determination
56 days
across 2,716 determinations
Slowest 20% take
154+ days
the figure worth planning around
Against NSW
-4 days
the NSW median is 60 days
Approved as CDC
72%
7,597 complying development certificates
Who determines applications here
Council staff under delegation60.5% · 1,658
Council (delegation not specified)34.5% · 946
Local Planning Panel2.6% · 72
Regional or Sydney planning panel1.3% · 36

An application determined under delegation is decided by the assessing officer. Anything referred to a panel or the elected body is decided in a public meeting and adds a meeting cycle to the timeline. Where the council recorded only “Council” it did not say which, so that row is left as published.

3.1% of applications in Campbelltown City Council sought a clause 4.6 variation to a development standard, and 67% of those variations were granted (61 of 91). 8.6% of DAs lodged were withdrawn before a determination was made. On the CDC side, 12.3% of certificates lodged were rejected rather than accepted, at an average declared cost of $445,956.

Why DAs get refused in Campbelltown City Council

Grounds cited across 144 refused applications, read from the council's own notices of determination. Most recent determination indexed: July 2026. Most refusals cite several grounds at once, so these overlap.

Contrary to the public interest (s4.15(1)(e))115 refusals
111 of these treated it as a decisive ground
Insufficient information submitted by applicant99 refusals
79 of these treated it as a decisive ground
Site not suitable for the development (s4.15(1)(c))78 refusals
74 of these treated it as a decisive ground
Stormwater, drainage or flooding55 refusals
42 of these treated it as a decisive ground
Streetscape / neighbourhood character incompatibility51 refusals
25 of these treated it as a decisive ground
Parking shortfall, traffic or vehicular access47 refusals
34 of these treated it as a decisive ground
Other ground not covered above41 refusals
22 of these treated it as a decisive ground
Setbacks or building envelope non-compliance40 refusals
19 of these treated it as a decisive ground
Read the council's exact wording

Behind each ground above sits the verbatim paragraph the assessing officer wrote, the LEP and DCP clauses it was tested against, and the address and DA number so you can pull the notice yourself. 1,087 grounds across Campbelltown City Council are indexed this way.

See the grounds in full

Conditions you should expect

Approval is not the finish line — every consent arrives with conditions. This is what Campbelltown City Council actually imposes, measured from the consent notices it has published.

Conditions marked costs money are the ones to budget for — contributions, bonds, specialist reports and public-domain works.

99%Appoint a principal certifier
93%Construction certificate before works start
90%Sydney Water approval (Section 73)COSTS MONEY
89%Erosion and sediment control
71%Build in accordance with the approved plans
70%Stormwater / on-site detentionCOSTS MONEY
67%Vehicular crossing, footpath and kerb worksCOSTS MONEY
61%Landscaping to be implemented and maintainedCOSTS MONEY
61%BASIX commitments
46%Waste management plan
42%Acoustic / noise limitsCOSTS MONEY
31%Section 68 Local Government Act approvalCOSTS MONEY

Based on 1,814 approvals with a published notice of determination · 6 of the conditions above carry a cost. A condition on most approvals is effectively standard; it is not a guarantee of what any individual consent will say.

Development type mix

What people are building in Campbelltown City Council. Ranked by DA volume.

Other3,073
Dual occupancy545
Alterations & additions359
Subdivision334
Change of use109
Commercial69
Residential flat building59

Development cost distribution

Estimated development cost ranges reported on Campbelltown City Council DAs.

Under $100k1,380
$100k – $500k1,533
$500k – $1M1,019
$1M – $5M422
$5M+237

Campbelltown City Council DAs — common questions

Answered from this council's own determinations. Where a council has not published a figure, the question is left out rather than guessed.

How many development applications does Campbelltown City Council handle?

Plan Advice holds 4,658 development applications for Campbelltown City Council, 1,983 of them lodged in the last 12 months. The figures on this page are counted from that register, not estimated.

How long does a DA take in Campbelltown City Council?

The median assessment time is 58 days for FY25-26, after a median 4 days to get the application accepted for lodgement. That is the council's own reported figure from the NSW Planning Portal league tables, so it covers every DA they determined — not a sample.

How long does the council take to determine a DA in Campbelltown City Council?

The median is 56 days from lodgement to determination across 2,716 applications determined in the last 5 years, and the slowest fifth take 154 days or more. The NSW median is 60 days. Counted from the NSW Planning Portal open data, so it covers every application — not a sample.

Who decides development applications in Campbelltown City Council?

60.5% of determinations were made by council staff under delegated authority. council (delegation not specified) determined 34.5%, local planning panel determined 2.6%, regional or sydney planning panel determined 1.3%. Anything referred to a panel or the elected body is decided in a public meeting, which adds a meeting cycle.

Does Campbelltown City Council approve clause 4.6 variations?

3.1% of applications sought a variation to a development standard, and 67% of those were granted (61 of 91 in the last 5 years).

Can I use a CDC instead of a DA in Campbelltown City Council?

72% of approvals in this LGA went through as complying development (7,597 certificates in the last 5 years), and 12.3% of CDC applications lodged were rejected rather than accepted. A CDC only applies if the proposal meets every development standard in the Codes SEPP.

Why are DAs refused in Campbelltown City Council?

Across 144 refused applications, the grounds cited most often are insufficient information submitted by applicant (99 refusals), contrary to the public interest (s4.15(1)(e)) (115 refusals), stormwater, drainage or flooding (55 refusals). These are read from the council's own notices of determination, and most refusals cite several grounds at once.

What kinds of development are most common in Campbelltown City Council?

The most frequent application types are dual occupancy (545), alterations & additions (359), subdivision (334).

How often is a clause 4.6 variation used in Campbelltown City Council?

121 applications — 2.6% of the register — sought a clause 4.6 variation to a development standard.

Most recent development applications

Sampled from the NSW Planning Portal open-data feed.

PAN-674692
5 WILLOWDALE DRIVE DENHAM COURT 2565
Other · lodged 2026-09-11T20:42:58.340
$16,500
PAN-674625
17-23 AIRDS ROAD MINTO 2566
Change of use · lodged 2026-09-11T20:42:25.040
PAN-674595
1 FOVEAUX PLACE AIRDS 2560
Subdivision · lodged 2026-09-11T20:42:05.860
$2,348,145
PAN-674555
84 BISCAY CIRCUIT MENANGLE PARK 2563
Dual occupancy · lodged 2026-09-11T20:41:30.780
$600,000
PAN-674537
9 BUNYIP AVENUE GILEAD 2560
Other · lodged 2026-09-11T20:41:16.723
$55,000
Assessing a property in Campbelltown City Council?

Get a free, instant AI-powered analysis of your property's zoning, planning controls and likely DA outcome — grounded in Plan Advice's 129,723-determination NSW precedent library.

Start free assessment →
Nearby councils: canterbury bankstown · carrathool · central coast · central darling · cessnock · canada bay · parramatta · clarence valley · cobar · coffs harbour · coolamon · coonamble — or see DA statistics for all 129 NSW councils.