Canterbury-Bankstown Council — Development Application Data
With 3169 development applications lodged in the past 12 months alone, Canterbury-Bankstown Council processes one of the highest DA volumes across Sydney, reflecting strong development activity in this diverse LGA. Since 2021, council records show 8121 applications on file, with Other developments accounting for 4041 applications, followed by 2055 dual occupancies—a popular choice for property investors seeking to maximise site potential. The median assessment time sits at 80 days, while just 3.69% of applications relied on Clause 4.6 variations to development standards. Development activity spans all cost brackets, from 2978 applications under $100k through to 270 projects valued above $5M, demonstrating opportunities for projects of every scale. Whether you're planning alterations, a dual occupancy, or a subdivision, understanding council's assessment patterns is essential to your application strategy. A Plan Advice AI-powered assessment for your Canterbury-Bankstown property takes seconds to run.
Determination outcomes
Real approval, refusal and withdrawal rates from finalised DAs in the Plan Advice enriched corpus.
Based on the 95.7% of DAs in our Canterbury-Bankstown Council corpus with a confirmed determination. Applications still under assessment, and any whose outcome the council has not published, are excluded rather than estimated.
How long a DA takes in Canterbury-Bankstown Council, and who decides it
Counted from every application Canterbury-Bankstown Council determined in the last 5 years, as published in the NSW Planning Portal open data. Timelines are lodgement to determination, so they include the time spent waiting on the applicant.
An application determined under delegation is decided by the assessing officer. Anything referred to a panel or the elected body is decided in a public meeting and adds a meeting cycle to the timeline. Where the council recorded only “Council” it did not say which, so that row is left as published.
4% of applications in Canterbury-Bankstown Council sought a clause 4.6 variation to a development standard, and 34.6% of those variations were granted (72 of 208). 11.8% of DAs lodged were withdrawn before a determination was made. On the CDC side, 13.6% of certificates lodged were rejected rather than accepted, at an average declared cost of $744,765.
Development type mix
What people are building in Canterbury-Bankstown Council. Ranked by DA volume.
Development cost distribution
Estimated development cost ranges reported on Canterbury-Bankstown Council DAs.
Canterbury-Bankstown Council DAs — common questions
Answered from this council's own determinations. Where a council has not published a figure, the question is left out rather than guessed.
How many development applications does Canterbury-Bankstown Council handle?
Plan Advice holds 8,239 development applications for Canterbury-Bankstown Council, 3,026 of them lodged in the last 12 months. The figures on this page are counted from that register, not estimated.
How long does a DA take in Canterbury-Bankstown Council?
The median assessment time is 80 days for FY25-26, after a median 4 days to get the application accepted for lodgement. That is the council's own reported figure from the NSW Planning Portal league tables, so it covers every DA they determined — not a sample.
How long does the council take to determine a DA in Canterbury-Bankstown Council?
The median is 59 days from lodgement to determination across 4,716 applications determined in the last 5 years, and the slowest fifth take 137 days or more. The NSW median is 60 days. Counted from the NSW Planning Portal open data, so it covers every application — not a sample.
Who decides development applications in Canterbury-Bankstown Council?
1.1% of determinations were made by council staff under delegated authority. council (delegation not specified) determined 94.4%, local planning panel determined 1.7%. Anything referred to a panel or the elected body is decided in a public meeting, which adds a meeting cycle.
Does Canterbury-Bankstown Council approve clause 4.6 variations?
4% of applications sought a variation to a development standard, and 34.6% of those were granted (72 of 208 in the last 5 years).
Can I use a CDC instead of a DA in Canterbury-Bankstown Council?
67.8% of approvals in this LGA went through as complying development (10,836 certificates in the last 5 years), and 13.6% of CDC applications lodged were rejected rather than accepted. A CDC only applies if the proposal meets every development standard in the Codes SEPP.
What share of DAs does Canterbury-Bankstown Council approve?
70.1% of the 4,352 determined applications we hold were approved and 14.1% were refused. We can read a determination for 95.7% of this council's DAs; the rest are counted as unknown rather than assumed approved.
What kinds of development are most common in Canterbury-Bankstown Council?
The most frequent application types are dual occupancy (2,072), alterations & additions (983), subdivision (290).
How often is a clause 4.6 variation used in Canterbury-Bankstown Council?
302 applications — 3.67% of the register — sought a clause 4.6 variation to a development standard.
Most recent development applications
Sampled from the NSW Planning Portal open-data feed.
Get a free, instant AI-powered analysis of your property's zoning, planning controls and likely DA outcome — grounded in Plan Advice's 129,723-determination NSW precedent library.
Start free assessment →