City of Parramatta — Development Application Data
With 3178 development applications lodged in the past 12 months, City of Parramatta handles one of the highest development volumes in metropolitan Sydney, reflecting the area's rapid urban transformation. Property owners here face a median 84-day assessment period, while 6.67% of applications rely on clause 4.6 variations to navigate planning controls. The council's 7119 applications since 2021 span diverse project types, from 3981 classified as other development to 1078 dual occupancies and 291 residential flat buildings. Cost distribution shows genuine range: 2683 applications under $100k sit alongside 443 projects exceeding $5M, indicating both incremental renovations and major urban renewal. Development in Parramatta's competitive market requires understanding council-specific assessment patterns and which planning standards frequently require variation requests. A Plan Advice AI-powered assessment for your City of Parramatta property delivers this strategic insight in seconds.
Determination outcomes
Real approval, refusal and withdrawal rates from finalised DAs in the Plan Advice enriched corpus.
Based on the 100% of DAs in our City of Parramatta corpus with a confirmed determination. Applications still under assessment, and any whose outcome the council has not published, are excluded rather than estimated.
How long a DA takes in City of Parramatta, and who decides it
Counted from every application City of Parramatta determined in the last 5 years, as published in the NSW Planning Portal open data. Timelines are lodgement to determination, so they include the time spent waiting on the applicant.
An application determined under delegation is decided by the assessing officer. Anything referred to a panel or the elected body is decided in a public meeting and adds a meeting cycle to the timeline. Where the council recorded only “Council” it did not say which, so that row is left as published.
7.7% of applications in City of Parramatta sought a clause 4.6 variation to a development standard, and 30.5% of those variations were granted (92 of 302). 6.9% of DAs lodged were withdrawn before a determination was made. On the CDC side, 14% of certificates lodged were rejected rather than accepted, at an average declared cost of $1,006,583.
Why DAs get refused in City of Parramatta
Grounds cited across 13 refused applications, read from the council's own notices of determination. Most recent determination indexed: August 2024. Most refusals cite several grounds at once, so these overlap.
Behind each ground above sits the verbatim paragraph the assessing officer wrote, the LEP and DCP clauses it was tested against, and the address and DA number so you can pull the notice yourself. 126 grounds across City of Parramatta are indexed this way.
See the grounds in fullDevelopment type mix
What people are building in City of Parramatta. Ranked by DA volume.
Development cost distribution
Estimated development cost ranges reported on City of Parramatta DAs.
City of Parramatta DAs — common questions
Answered from this council's own determinations. Where a council has not published a figure, the question is left out rather than guessed.
How many development applications does City of Parramatta handle?
Plan Advice holds 7,276 development applications for City of Parramatta, 3,049 of them lodged in the last 12 months. The figures on this page are counted from that register, not estimated.
How long does a DA take in City of Parramatta?
The median assessment time is 84 days for FY25-26, after a median 33 days to get the application accepted for lodgement. That is the council's own reported figure from the NSW Planning Portal league tables, so it covers every DA they determined — not a sample.
How long does the council take to determine a DA in City of Parramatta?
The median is 84 days from lodgement to determination across 3,756 applications determined in the last 5 years, and the slowest fifth take 164 days or more. The NSW median is 60 days. Counted from the NSW Planning Portal open data, so it covers every application — not a sample.
Who decides development applications in City of Parramatta?
32% of determinations were made by council staff under delegated authority. council (delegation not specified) determined 59.3%, local planning panel determined 3.2%, regional or sydney planning panel determined 1.8%. Anything referred to a panel or the elected body is decided in a public meeting, which adds a meeting cycle.
Does City of Parramatta approve clause 4.6 variations?
7.7% of applications sought a variation to a development standard, and 30.5% of those were granted (92 of 302 in the last 5 years).
Can I use a CDC instead of a DA in City of Parramatta?
66% of approvals in this LGA went through as complying development (7,593 certificates in the last 5 years), and 14% of CDC applications lodged were rejected rather than accepted. A CDC only applies if the proposal meets every development standard in the Codes SEPP.
What share of DAs does City of Parramatta approve?
97.3% of the 4,115 determined applications we hold were approved and 1.3% were refused. We can read a determination for 100% of this council's DAs; the rest are counted as unknown rather than assumed approved.
Why are DAs refused in City of Parramatta?
Across 13 refused applications, the grounds cited most often are stormwater, drainage or flooding (10 refusals), contrary to the public interest (s4.15(1)(e)) (12 refusals), sepp non-compliance (basix, codes, housing etc.) (4 refusals). These are read from the council's own notices of determination, and most refusals cite several grounds at once.
What kinds of development are most common in City of Parramatta?
The most frequent application types are dual occupancy (1,096), alterations & additions (914), residential flat building (303).
How often is a clause 4.6 variation used in City of Parramatta?
483 applications — 6.64% of the register — sought a clause 4.6 variation to a development standard.
Most recent development applications
Sampled from the NSW Planning Portal open-data feed.