Weddin Shire Council — Development Application Data

A live snapshot of development activity in Weddin Shire Council — sourced from NSW Government open data and the 413,770-DA Plan Advice corpus. Refreshed automatically. Data reflects the most recent NSW Planning Portal open-data feeds, counted application by application.

DAs on file
308
Since 2021
Lodged last 12m
47
Median assessment
24 days
Clause 4.6 rate
8.1%
Development standard variations

How long a DA takes in Weddin Shire Council, and who decides it

Counted from every application Weddin Shire Council determined in the last 5 years, as published in the NSW Planning Portal open data. Timelines are lodgement to determination, so they include the time spent waiting on the applicant.

Median determination
24 days
across 233 determinations
Slowest 20% take
48+ days
the figure worth planning around
Against NSW
-36 days
the NSW median is 60 days
Approved as CDC
21.8%
66 complying development certificates
Who determines applications here
Council (delegation not specified)65.8% · 156
Council staff under delegation32.1% · 76

An application determined under delegation is decided by the assessing officer. Anything referred to a panel or the elected body is decided in a public meeting and adds a meeting cycle to the timeline. Where the council recorded only “Council” it did not say which, so that row is left as published.

8% of applications in Weddin Shire Council sought a clause 4.6 variation to a development standard, and 10.5% of those variations were granted (2 of 19). 1.3% of DAs lodged were withdrawn before a determination was made. On the CDC side, 47% of certificates lodged were rejected rather than accepted, at an average declared cost of $137,922.

Development type mix

What people are building in Weddin Shire Council. Ranked by DA volume.

Erection of a new structure108
Shed67
Dwelling house46
Alterations or additions to an existing building or structure34
Garages, carports and car parking spaces29
Dwelling23
Residential Accommodation21
Subdivision19

Development cost distribution

Estimated development cost ranges reported on Weddin Shire Council DAs.

Under $100k210
$100k – $500k75
$500k – $1M15
$1M – $5M7
$5M+1

Weddin Shire Council DAs — common questions

Answered from this council's own determinations. Where a council has not published a figure, the question is left out rather than guessed.

How many development applications does Weddin Shire Council handle?

Plan Advice holds 308 development applications for Weddin Shire Council, 47 of them lodged in the last 12 months. The figures on this page are counted from that register, not estimated.

How long does a DA take in Weddin Shire Council?

The median assessment time is 24 days. That is the council's own reported figure from the NSW Planning Portal league tables, so it covers every DA they determined — not a sample.

How long does the council take to determine a DA in Weddin Shire Council?

The median is 24 days from lodgement to determination across 233 applications determined in the last 5 years, and the slowest fifth take 48 days or more. The NSW median is 60 days. Counted from the NSW Planning Portal open data, so it covers every application — not a sample.

Who decides development applications in Weddin Shire Council?

32.1% of determinations were made by council staff under delegated authority. council (delegation not specified) determined 65.8%. Anything referred to a panel or the elected body is decided in a public meeting, which adds a meeting cycle.

Does Weddin Shire Council approve clause 4.6 variations?

8% of applications sought a variation to a development standard, and 10.5% of those were granted (2 of 19 in the last 5 years).

Can I use a CDC instead of a DA in Weddin Shire Council?

21.8% of approvals in this LGA went through as complying development (66 certificates in the last 5 years), and 47% of CDC applications lodged were rejected rather than accepted. A CDC only applies if the proposal meets every development standard in the Codes SEPP.

What kinds of development are most common in Weddin Shire Council?

The most frequent application types are erection of a new structure (108), shed (67), dwelling house (46).

How often is a clause 4.6 variation used in Weddin Shire Council?

25 applications — 8.12% of the register — sought a clause 4.6 variation to a development standard.

Most recent development applications

Sampled from the NSW Planning Portal open-data feed.

PAN-676240
30 FORBES STREET GRENFELL 2810
Dwelling house · lodged 2026-09-17
$50,000
PAN-673855
1 BRUNDAH STREET GRENFELL 2810
Rural industry · lodged 2026-09-17
PAN-673848
WEST STREET GRENFELL 2810
Rural industry · lodged 2026-09-17
PAN-673828
3 GRAFTON STREET GRENFELL 2810
Rural industry · lodged 2026-09-17
DA 31/2026
147 MANGANESE ROAD GRENFELL 2810
Shed · lodged 2026-09-14
$439,780
Assessing a property in Weddin Shire Council?

Get a free, instant AI-powered analysis of your property's zoning, planning controls and likely DA outcome — grounded in Plan Advice's 413,770-DA NSW corpus.

Start free assessment →
Nearby councils: wentworth · willoughby · wingecarribee · wollondilly · wollongong · woollahra · yass valley · albury · armidale · ballina · balranald · bathurst — or see DA statistics for all 129 NSW councils.