Richmond Valley Council — Development Application Data
A live snapshot of development activity in Richmond Valley Council — sourced from NSW Government open data and the 413,770-DA Plan Advice corpus. Refreshed automatically. Data reflects the most recent NSW Planning Portal open-data feeds, counted application by application.
How long a DA takes in Richmond Valley Council, and who decides it
Counted from every application Richmond Valley Council determined in the last 5 years, as published in the NSW Planning Portal open data. Timelines are lodgement to determination, so they include the time spent waiting on the applicant.
An application determined under delegation is decided by the assessing officer. Anything referred to a panel or the elected body is decided in a public meeting and adds a meeting cycle to the timeline. Where the council recorded only “Council” it did not say which, so that row is left as published.
3.3% of applications in Richmond Valley Council sought a clause 4.6 variation to a development standard, and 114.7% of those variations were granted (39 of 34). 2.7% of DAs lodged were withdrawn before a determination was made. On the CDC side, 44.3% of certificates lodged were rejected rather than accepted, at an average declared cost of $207,929.
Development type mix
What people are building in Richmond Valley Council. Ranked by DA volume.
Development cost distribution
Estimated development cost ranges reported on Richmond Valley Council DAs.
Richmond Valley Council DAs — common questions
Answered from this council's own determinations. Where a council has not published a figure, the question is left out rather than guessed.
How many development applications does Richmond Valley Council handle?
Plan Advice holds 1,329 development applications for Richmond Valley Council, 215 of them lodged in the last 12 months. The figures on this page are counted from that register, not estimated.
How long does a DA take in Richmond Valley Council?
The median assessment time is 42 days. That is the council's own reported figure from the NSW Planning Portal league tables, so it covers every DA they determined — not a sample.
How long does the council take to determine a DA in Richmond Valley Council?
The median is 42 days from lodgement to determination across 993 applications determined in the last 5 years, and the slowest fifth take 69 days or more. The NSW median is 60 days. Counted from the NSW Planning Portal open data, so it covers every application — not a sample.
Who decides development applications in Richmond Valley Council?
8.1% of determinations were made by council staff under delegated authority. council (delegation not specified) determined 90.2%. Anything referred to a panel or the elected body is decided in a public meeting, which adds a meeting cycle.
Does Richmond Valley Council approve clause 4.6 variations?
3.3% of applications sought a variation to a development standard, and 114.7% of those were granted (39 of 34 in the last 5 years).
Can I use a CDC instead of a DA in Richmond Valley Council?
17.7% of approvals in this LGA went through as complying development (221 certificates in the last 5 years), and 44.3% of CDC applications lodged were rejected rather than accepted. A CDC only applies if the proposal meets every development standard in the Codes SEPP.
What kinds of development are most common in Richmond Valley Council?
The most frequent application types are erection of a new structure (397), shed (275), dwelling house (217).
How often is a clause 4.6 variation used in Richmond Valley Council?
38 applications — 2.86% of the register — sought a clause 4.6 variation to a development standard.
Most recent development applications
Sampled from the NSW Planning Portal open-data feed.
Get a free, instant AI-powered analysis of your property's zoning, planning controls and likely DA outcome — grounded in Plan Advice's 413,770-DA NSW corpus.