Greater Hume Shire Council — Development Application Data

A live snapshot of development activity in Greater Hume Shire Council — sourced from NSW Government open data and the 413,770-DA Plan Advice corpus. Refreshed automatically. Data reflects the most recent NSW Planning Portal open-data feeds, counted application by application.

DAs on file
1,261
Since 2021
Lodged last 12m
181
Median assessment
32 days
Clause 4.6 rate
1.3%
Development standard variations

How long a DA takes in Greater Hume Shire Council, and who decides it

Counted from every application Greater Hume Shire Council determined in the last 5 years, as published in the NSW Planning Portal open data. Timelines are lodgement to determination, so they include the time spent waiting on the applicant.

Median determination
32 days
across 957 determinations
Slowest 20% take
58+ days
the figure worth planning around
Against NSW
-28 days
the NSW median is 60 days
Approved as CDC
32%
460 complying development certificates
Who determines applications here
Council (delegation not specified)55% · 532
Council staff under delegation43.7% · 423

An application determined under delegation is decided by the assessing officer. Anything referred to a panel or the elected body is decided in a public meeting and adds a meeting cycle to the timeline. Where the council recorded only “Council” it did not say which, so that row is left as published.

1.2% of applications in Greater Hume Shire Council sought a clause 4.6 variation to a development standard, and 58.3% of those variations were granted (7 of 12). 3.3% of DAs lodged were withdrawn before a determination was made. On the CDC side, 20.9% of certificates lodged were rejected rather than accepted, at an average declared cost of $249,206.

Development type mix

What people are building in Greater Hume Shire Council. Ranked by DA volume.

Shed412
Erection of a new structure411
Dwelling house149
Dwelling132
Subdivision85
Alterations or additions to an existing building or structure80
Subdivision of land73
Demolition71

Development cost distribution

Estimated development cost ranges reported on Greater Hume Shire Council DAs.

Under $100k793
$100k – $500k264
$500k – $1M129
$1M – $5M55
$5M+8

Greater Hume Shire Council DAs — common questions

Answered from this council's own determinations. Where a council has not published a figure, the question is left out rather than guessed.

How many development applications does Greater Hume Shire Council handle?

Plan Advice holds 1,261 development applications for Greater Hume Shire Council, 181 of them lodged in the last 12 months. The figures on this page are counted from that register, not estimated.

How long does a DA take in Greater Hume Shire Council?

The median assessment time is 32 days. That is the council's own reported figure from the NSW Planning Portal league tables, so it covers every DA they determined — not a sample.

How long does the council take to determine a DA in Greater Hume Shire Council?

The median is 32 days from lodgement to determination across 957 applications determined in the last 5 years, and the slowest fifth take 58 days or more. The NSW median is 60 days. Counted from the NSW Planning Portal open data, so it covers every application — not a sample.

Who decides development applications in Greater Hume Shire Council?

43.7% of determinations were made by council staff under delegated authority. council (delegation not specified) determined 55%. Anything referred to a panel or the elected body is decided in a public meeting, which adds a meeting cycle.

Does Greater Hume Shire Council approve clause 4.6 variations?

1.2% of applications sought a variation to a development standard, and 58.3% of those were granted (7 of 12 in the last 5 years).

Can I use a CDC instead of a DA in Greater Hume Shire Council?

32% of approvals in this LGA went through as complying development (460 certificates in the last 5 years), and 20.9% of CDC applications lodged were rejected rather than accepted. A CDC only applies if the proposal meets every development standard in the Codes SEPP.

What kinds of development are most common in Greater Hume Shire Council?

The most frequent application types are shed (412), erection of a new structure (411), dwelling house (149).

How often is a clause 4.6 variation used in Greater Hume Shire Council?

16 applications — 1.27% of the register — sought a clause 4.6 variation to a development standard.

Most recent development applications

Sampled from the NSW Planning Portal open-data feed.

PAN-676114
1 KINVARA WAY CULCAIRN 2660
Erection of a new structure · lodged 2026-09-17
$149,745
PAN-674887
82 ADAMS STREET JINDERA 2642
Shed · lodged 2026-09-17
$43,245
PAN-674598
14A WALLACE STREET HOLBROOK 2644
Erection of a new structure · lodged 2026-09-17
$200,000
PAN-674284
72 ALBURY STREET HOLBROOK 2644
Demolition · lodged 2026-09-17
$27,803
10.2026.114.1
92 BILLABONG STREET WALBUNDRIE 2642
Shed · lodged 2026-08-21
$40,104
Assessing a property in Greater Hume Shire Council?

Get a free, instant AI-powered analysis of your property's zoning, planning controls and likely DA outcome — grounded in Plan Advice's 413,770-DA NSW corpus.

Start free assessment →