Ku-ring-gai Council — Development Application Data
Development assessment times in Ku-ring-gai Council run longer than most Sydney councils, with a median of 94 days from lodgement to determination. The council processed 1,310 applications in the past year, drawing from a database of 4,176 DAs lodged since 2021. One in six applications relies on a Clause 4.6 variation to exceed a development standard such as height or floor space ratio. While the majority of proposals fall into unclassified categories, alterations and additions account for 862 applications, followed by residential flat buildings at 144 and dual occupancies at 93. Development costs span the full spectrum: 1,295 applications valued under $100,000, 951 between $100,000 and $500,000, 750 between $500,000 and $1 million, 832 between $1 million and $5 million, and 188 exceeding $5 million. A Plan Advice AI assessment for your Ku-ring-gai property delivers a detailed feasibility report in seconds.
Determination outcomes
Real approval, refusal and withdrawal rates from finalised DAs in the Plan Advice enriched corpus.
Based on the 100% of DAs in our Ku-ring-gai Council corpus with a confirmed determination. Applications still under assessment, and any whose outcome the council has not published, are excluded rather than estimated.
How long a DA takes in Ku-ring-gai Council, and who decides it
Counted from every application Ku-ring-gai Council determined in the last 5 years, as published in the NSW Planning Portal open data. Timelines are lodgement to determination, so they include the time spent waiting on the applicant.
An application determined under delegation is decided by the assessing officer. Anything referred to a panel or the elected body is decided in a public meeting and adds a meeting cycle to the timeline. Where the council recorded only “Council” it did not say which, so that row is left as published.
17.5% of applications in Ku-ring-gai Council sought a clause 4.6 variation to a development standard, and 21.2% of those variations were granted (112 of 529). 8.8% of DAs lodged were withdrawn before a determination was made. On the CDC side, 12.6% of certificates lodged were rejected rather than accepted, at an average declared cost of $620,132.
Why DAs get refused in Ku-ring-gai Council
Grounds cited across 8 refused applications, read from the council's own notices of determination. Most recent determination indexed: August 2025. Most refusals cite several grounds at once, so these overlap.
Behind each ground above sits the verbatim paragraph the assessing officer wrote, the LEP and DCP clauses it was tested against, and the address and DA number so you can pull the notice yourself. 23 grounds across Ku-ring-gai Council are indexed this way.
See the grounds in fullDevelopment type mix
What people are building in Ku-ring-gai Council. Ranked by DA volume.
Development cost distribution
Estimated development cost ranges reported on Ku-ring-gai Council DAs.
Ku-ring-gai Council DAs — common questions
Answered from this council's own determinations. Where a council has not published a figure, the question is left out rather than guessed.
How many development applications does Ku-ring-gai Council handle?
Plan Advice holds 4,254 development applications for Ku-ring-gai Council, 1,252 of them lodged in the last 12 months. The figures on this page are counted from that register, not estimated.
How long does a DA take in Ku-ring-gai Council?
The median assessment time is 94 days for FY25-26, after a median 10 days to get the application accepted for lodgement. That is the council's own reported figure from the NSW Planning Portal league tables, so it covers every DA they determined — not a sample.
How long does the council take to determine a DA in Ku-ring-gai Council?
The median is 99 days from lodgement to determination across 2,854 applications determined in the last 5 years, and the slowest fifth take 154 days or more. The NSW median is 60 days. Counted from the NSW Planning Portal open data, so it covers every application — not a sample.
Does Ku-ring-gai Council approve clause 4.6 variations?
17.5% of applications sought a variation to a development standard, and 21.2% of those were granted (112 of 529 in the last 5 years).
Can I use a CDC instead of a DA in Ku-ring-gai Council?
60.3% of approvals in this LGA went through as complying development (4,600 certificates in the last 5 years), and 12.6% of CDC applications lodged were rejected rather than accepted. A CDC only applies if the proposal meets every development standard in the Codes SEPP.
What share of DAs does Ku-ring-gai Council approve?
97.4% of the 1,858 determined applications we hold were approved and 2.6% were refused. We can read a determination for 100% of this council's DAs; the rest are counted as unknown rather than assumed approved.
Why are DAs refused in Ku-ring-gai Council?
Across 8 refused applications, the grounds cited most often are contrary to the public interest (s4.15(1)(e)) (6 refusals), insufficient information submitted by applicant (2 refusals), other ground not covered above (1 refusals). These are read from the council's own notices of determination, and most refusals cite several grounds at once.
What kinds of development are most common in Ku-ring-gai Council?
The most frequent application types are alterations & additions (866), residential flat building (147), dual occupancy (96).
How often is a clause 4.6 variation used in Ku-ring-gai Council?
698 applications — 16.41% of the register — sought a clause 4.6 variation to a development standard.
Most recent development applications
Sampled from the NSW Planning Portal open-data feed.