Mid-Coast Council — Development Application Data
A live snapshot of development activity in Mid-Coast Council — sourced from NSW Government open data and the 413,770-DA Plan Advice corpus. Refreshed automatically. Data reflects the most recent NSW Planning Portal open-data feeds, counted application by application.
How long a DA takes in Mid-Coast Council, and who decides it
Counted from every application Mid-Coast Council determined in the last 5 years, as published in the NSW Planning Portal open data. Timelines are lodgement to determination, so they include the time spent waiting on the applicant.
An application determined under delegation is decided by the assessing officer. Anything referred to a panel or the elected body is decided in a public meeting and adds a meeting cycle to the timeline. Where the council recorded only “Council” it did not say which, so that row is left as published.
2.3% of applications in Mid-Coast Council sought a clause 4.6 variation to a development standard, and 100% of those variations were granted (140 of 140). 3.4% of DAs lodged were withdrawn before a determination was made. On the CDC side, 22.3% of certificates lodged were rejected rather than accepted, at an average declared cost of $221,359.
Development type mix
What people are building in Mid-Coast Council. Ranked by DA volume.
Development cost distribution
Estimated development cost ranges reported on Mid-Coast Council DAs.
Mid-Coast Council DAs — common questions
Answered from this council's own determinations. Where a council has not published a figure, the question is left out rather than guessed.
How many development applications does Mid-Coast Council handle?
Plan Advice holds 8,107 development applications for Mid-Coast Council, 1,066 of them lodged in the last 12 months. The figures on this page are counted from that register, not estimated.
How long does a DA take in Mid-Coast Council?
The median assessment time is 44 days. That is the council's own reported figure from the NSW Planning Portal league tables, so it covers every DA they determined — not a sample.
How long does the council take to determine a DA in Mid-Coast Council?
The median is 44 days from lodgement to determination across 6,161 applications determined in the last 5 years, and the slowest fifth take 121 days or more. The NSW median is 60 days. Counted from the NSW Planning Portal open data, so it covers every application — not a sample.
Who decides development applications in Mid-Coast Council?
41.6% of determinations were made by council staff under delegated authority. council (delegation not specified) determined 57.5%. Anything referred to a panel or the elected body is decided in a public meeting, which adds a meeting cycle.
Does Mid-Coast Council approve clause 4.6 variations?
2.3% of applications sought a variation to a development standard, and 100% of those were granted (140 of 140 in the last 5 years).
Can I use a CDC instead of a DA in Mid-Coast Council?
25.9% of approvals in this LGA went through as complying development (2,180 certificates in the last 5 years), and 22.3% of CDC applications lodged were rejected rather than accepted. A CDC only applies if the proposal meets every development standard in the Codes SEPP.
What kinds of development are most common in Mid-Coast Council?
The most frequent application types are erection of a new structure (2,204), dwelling house (1,410), dwelling (1,349).
How often is a clause 4.6 variation used in Mid-Coast Council?
168 applications — 2.07% of the register — sought a clause 4.6 variation to a development standard.
Most recent development applications
Sampled from the NSW Planning Portal open-data feed.
Get a free, instant AI-powered analysis of your property's zoning, planning controls and likely DA outcome — grounded in Plan Advice's 413,770-DA NSW corpus.
Start free assessment →